|
This page last changed on Jan 31, 2008 by jbirch.
Outline of instrument plan for Jan-Jun, 2008
Mack has been cold tested with new hand and new valves and Roman Flush run to check tubing.
Temp calibration Jan 29-Feb 5.
Science gets MACK Feb 6 and will prep reagents, generate mission script, run sub-protocol tests
- One month cold test of Mack w/ his new valves/hand starting Feb 14.
- OBJECTIVE: get through a full carousel of pucks
- test should last most of 4 weeks (although 3 weeks would be acceptable)
- March 6 is earliest we pull and deem a success. Once pulled, we replace with Bruce for box test.
- Prep for Spring deployments (Mar 14 -->Mar 19)
- Deploy MACK (March 20-Shana Rae)
- Recover MACK Apr 10, Deploy BRUCE -- Shana Rae
- Recover BRUCE, Deploy MACK (May 1 -- Zephyr)
- Recover BRUCE (May 27), Deploy both MACK and NEO (May 28 -- Zephyr)
- End mission Jun 30.
(Revised 31 Jan 2008)
|